Given the following information regarding a project involving an initial public offering (IPO):
Activities Description Duration (weeks) Predecessors
a. Check feasibility 3 β
b. Determine funding 1 β
c. Find possible banks 3 a
d. Select two possible 4 a
e. Interview two banks 4 b
f. Analyze funding costs 5 b
g. Determine chance of success 2 c ,e
h Sign contract 3 f
a) Draw the network.
b) What is the critical path?
c) Calculate the float for each activity.
d) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks? Three extra weeks?

Answers: 3


Another question on Business

Business, 22.06.2019 08:30
Match each item to check for while reconciling a bank account with the document to which it relates.(there's not just one answer)1. balancing account statement2. balancing check registera. nsf feesb. deposits in transitc. interest earnedd. bank errors
Answers: 2

Business, 22.06.2019 23:40
John has been working as a tutor for $300 a semester. when the university raises the price it pays tutors to $400, jasmine enters the market and begins tutoring as well. how much does producer surplus rise as a result of this price increase?
Answers: 1

Business, 23.06.2019 01:00
"consists of larger societal forces that affect how a company engages and serves its customers."
Answers: 1

You know the right answer?
Given the following information regarding a project involving an initial public offering (IPO):
Questions









Business, 30.07.2019 17:30


Biology, 30.07.2019 17:30









Mathematics, 30.07.2019 17:30