A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

Please answer fast

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 02:30
Your boss wants you to configure his laptop so that he can access the company network when he is on the road. you suggest a vpn connection to him. he is very concerned about security and asks you how secure vpn is. what do you tell him?
Answers: 1
question
Computers and Technology, 23.06.2019 04:40
The narrative structure of the popular movies can be broken down into
Answers: 3
question
Computers and Technology, 24.06.2019 07:00
Guys do you know sh27 cause he hacked me : ( pidgegunderson my old user
Answers: 2
question
Computers and Technology, 24.06.2019 07:30
John recently worked on a project about various programming languages. he learned that though procedural language programs are useful, they have disadvantages too. what is a disadvantage of programs written in procedural languages? a. programs do not represent data complexity. b. programs take more time to execute. c. programs are prone to security threats. d. programs do not interface with multiple platforms.
Answers: 3
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
History, 16.10.2019 06:00
question
Mathematics, 16.10.2019 06:00
question
Mathematics, 16.10.2019 06:00
Questions on the website: 13722363