Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a 0.90 probability that the project will be completed before approximately day .
i.98
ii.108
iii.109
iv.115
v.118

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 21:30
Ijust need these 2 questions answered (the second pic is just confirmation i'm not confident in that answer)
Answers: 1
question
Mathematics, 21.06.2019 21:30
How does reflecting or rotating a figure change the interior angles of the figure?
Answers: 2
question
Mathematics, 21.06.2019 22:00
The coordinates r(1, -3), s(3, -1) t(5, -7) form what type of polygon? a right triangle an acute triangle an equilateral triangle an obtuse triangle
Answers: 1
question
Mathematics, 21.06.2019 23:30
Consider the first four terms of the sequence below. what is the 8th term of this sequence?
Answers: 1
You know the right answer?
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a vari...
Questions
question
Mathematics, 22.04.2020 18:51
question
Mathematics, 22.04.2020 18:52
Questions on the website: 13722360