A person can do a job in 6 days. Another can do the same job in 4 days. If they work together, how long do they need to finish the job?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Players on the school soccer team are selling candles to raise money for an upcoming trip. each player has 24 candles to sell. if a player sells 4 candles a profit of$30 is made. if he sells 12 candles a profit of $70 is made
Answers: 2
question
Mathematics, 21.06.2019 18:40
Which of the following represents the range of the graph of f(x) below
Answers: 1
question
Mathematics, 21.06.2019 23:20
The graph of y=x3 is transformed as shown in the graph below. which equation represents the transformed function?
Answers: 1
question
Mathematics, 22.06.2019 00:30
Given abc find the values of x and y. in your final answer, include all of your calculations.
Answers: 1
You know the right answer?
A person can do a job in 6 days. Another can do the same job in 4 days. If they work together, how l...
Questions
question
Computers and Technology, 01.09.2019 21:00
question
Mathematics, 01.09.2019 21:00
Questions on the website: 13722363