You work on a concrete crew starting a construction project. Once the pouring begins, it must continue non-stop until it is completed. Your crew will work an 8-hour shift along with two
other crews. The total project requires 175,000 yards of concrete. Your supervisor estimates
that each crew will pour around 1200 yards per hour. How many consecutive days should you
plan to work on this project?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
Aball is dropped from a height of 10m above the ground. it bounce to 90% of its previous height on each bounce. what is the approximate height that the ball bounce to the fourth bounce?
Answers: 2
question
Mathematics, 21.06.2019 21:30
The expression 1.01*1.005(^t) gives the amount of money, in thousands of dollars, in carter's savings account (t) years after he opens it. what does 1.01 represent in this expression?
Answers: 1
question
Mathematics, 22.06.2019 00:30
Officer brimberry wrote 32 tickets for traffic violations last week, but only 4 tickets this week. what is the percent decrease? give your answer to the nearest tenth of a percent.
Answers: 1
question
Mathematics, 22.06.2019 04:30
Roxanna earns 150% her normal hourly rate for overtime pay. last week, roxanna earned $72.00 in overtime pay for 4 hours. what is roxana's normal hourly pay?
Answers: 1
You know the right answer?
You work on a concrete crew starting a construction project. Once the pouring begins, it must conti...
Questions
question
Mathematics, 20.09.2020 15:01
question
Mathematics, 20.09.2020 15:01
question
Mathematics, 20.09.2020 15:01
Questions on the website: 13722361