subject
Mathematics, 18.03.2021 01:50 jahzz

The expected activity time in PERT analysis is calculated as: the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b. the sum of the optimistic, pessimistic, and most likely times, divided by six. the simple average of the optimistic, pessimistic, and most likely times. the sum of the activity variances, divided by six. the sum of the optimistic, pessimistic, and most likely times.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
Find the y-intercept and x-intercept for the equation 5x-3y=60 what is the y-intercept
Answers: 1
question
Mathematics, 21.06.2019 20:10
In the diagram, the ratios of two pairs of corresponding sides are equal to prove that almn - axyz by the sas similarity theorem, it also needs to be shown that x 6 z un z zz un = 2x zləzz lezy
Answers: 1
question
Mathematics, 21.06.2019 23:30
Solve for x and select the correct answer
Answers: 1
question
Mathematics, 22.06.2019 02:20
The diagram shows a cuboid abcdefgh abcd is a square with area 25cm². find the volume of the cuboid.
Answers: 3
You know the right answer?
The expected activity time in PERT analysis is calculated as: the weighted average of a, m, and b, w...
Questions
question
Mathematics, 25.05.2021 23:00
question
Mathematics, 25.05.2021 23:00
question
Geography, 25.05.2021 23:00
question
Spanish, 25.05.2021 23:00
question
Mathematics, 25.05.2021 23:00
question
Mathematics, 25.05.2021 23:00
question
Spanish, 25.05.2021 23:00
Questions on the website: 13722360