540 men can construct a building in 7 months. how many men should be removed from work to finish the building in 9 months? ( someone explain it so that i can learn it)

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Solve the system of equations. y= 2x y= x^2 - 15
Answers: 1
question
Mathematics, 21.06.2019 17:00
Aswimming pool is a rectangle with semicircles on the end. the rectangle is 12 meters wide and 30 meters long. the diameter and width of the swimming pool are equal. sketch and label an overhead diagram of the swimming pool. find the area of the swimming pool floor.
Answers: 1
question
Mathematics, 21.06.2019 18:20
If f(x)=-x^2+6x-1 and g(x)=3x^2-4x-1,find(f+g)(x)
Answers: 1
question
Mathematics, 21.06.2019 21:30
Janice determined there were 10 possible outcomes when tossing two coins and spinning a spinner numbered 1 through 6. what is the correct number? what might have been janice's error?
Answers: 3
You know the right answer?
540 men can construct a building in 7 months. how many men should be removed from work to finish the...
Questions
question
Mathematics, 08.02.2021 20:30
question
Mathematics, 08.02.2021 20:30
Questions on the website: 13722359