Mathematics, 08.06.2021 08:10 alexisgonzales4752

48 men were deployed to construct a bridge in 30 days. (a) By letting the number of men be m and the number of days needed to complete the
construction works be d, form an equation relating m and d.
(b) After 10 days, 8 men were sent to help in another project, how many days will the
construction work be delayed, assuming that all the men work at the same rate?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:30
Which expression demonstrates the use of the commutative property of addition in the first step of simplifying the expression (-1+i)+(21+5i)+0
Answers: 2
question
Mathematics, 21.06.2019 21:00
Oliver read for 450 minutes this month his goal was to read for 10% more minutes next month if all of her medicine go how many minutes will you read all during the next two months
Answers: 3
question
Mathematics, 21.06.2019 22:50
Type the correct answer in the box. use numerals instead of words. if necessary, use / for the fraction bar.
Answers: 1
question
Mathematics, 22.06.2019 04:00
Question 27 of 28 1 point what is the slope of the line shown below? (3,-2) (2,-4)
Answers: 1
You know the right answer?
48 men were deployed to construct a bridge in 30 days. (a) By letting the number of men be m and th...
Questions
question
English, 08.04.2021 21:50
question
Mathematics, 08.04.2021 21:50
question
Mathematics, 08.04.2021 21:50
Questions on the website: 13722361