It takes• 2 park keepers 1 hour to weed 2 flowerbeds• 3 park keepers 2 hours to prune 6 trees. At 9 a. m. one morning, 5 park keepers start work as follows. Number of park keepers Activity2 Weed: 2 flowerbeds3 Prune: 13 treesWhen one activity has been completed all the park keepers work on the other activity. You may assume that all the park keepers work at the same rate and are equally skilled. How long does it take for the park keepers to complete the pruning and weeding?You must show all your working.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
What percent of the circle below is shaded?
Answers: 1
question
Mathematics, 21.06.2019 19:30
If you could answer these your a life saver
Answers: 2
question
Mathematics, 21.06.2019 22:00
Match the scale and the actual area to the area of the corresponding scale drawing. scale: 1 inch to 4 feet actual area: 128 square feet scale: 1 inch to 7 feet actual area: 147 square feet scale: 1 inch to 8 feet actual area: 256 square feet scale: 1 inch to 5 feet actual area: 225 square feet area of scale drawing scale and actual area scale drawing area: 3 square inches arrowright scale drawing area: 8 square inches arrowright scale drawing area: 4 square inches arrowright scale drawing area: 9 square inches arrowright
Answers: 2
question
Mathematics, 21.06.2019 22:30
Which statements are true about additional information for proving that the triangles are congruent check all that apply
Answers: 1
You know the right answer?
It takes• 2 park keepers 1 hour to weed 2 flowerbeds• 3 park keepers 2 hours to prune 6 trees. At 9...
Questions
question
History, 29.11.2021 18:40
question
Social Studies, 29.11.2021 18:40
question
Mathematics, 29.11.2021 18:40
question
Computers and Technology, 29.11.2021 18:40
question
Mathematics, 29.11.2021 18:40
Questions on the website: 13722360