you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days and optimistic estimate of 12 days. what is the mean using the PERT technique

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
Astore has apples on sale for three dollars or 2 pounds how many pounds of apples can you buy for nine dollars if an apple is approximately 5 ounces how many apples can you buy for nine dollars
Answers: 1
question
Mathematics, 21.06.2019 20:20
If sin(x) = 0 and cos(x) = 1, what is tan(x)?
Answers: 1
question
Mathematics, 21.06.2019 22:10
What is the measure of sty in oo below? 130 310 230 50
Answers: 2
question
Mathematics, 22.06.2019 02:30
Jody bought 20 shares of amazon at the close price of $121.00. she bought 20 more shares a year later at the price of $127.00. two years later, she sold all of her shares at the price of $133.00. her broker charges $50 for each transaction. after all of these transactions, how much money did jody make?
Answers: 2
You know the right answer?
you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 day...
Questions
question
Physics, 01.11.2020 16:00
question
Business, 01.11.2020 16:00
question
Mathematics, 01.11.2020 16:10
question
Mathematics, 01.11.2020 16:10
question
Mathematics, 01.11.2020 16:10
question
Geography, 01.11.2020 16:10
Questions on the website: 13722361