Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?
Answers: 3
question
Mathematics, 22.06.2019 01:00
A+b= 17, ab=70, find the value of |a-b|
Answers: 3
question
Mathematics, 22.06.2019 03:30
The slope of the line passing through the points (2, 7) and (-4, 8) is
Answers: 2
question
Mathematics, 22.06.2019 03:30
Which of the following is true about the following construction of a tangent to a circle from a point outside of the circle?
Answers: 2
You know the right answer?
Fill in the blank with > ,< , or =: 2.5 2.45...
Questions
question
Mathematics, 15.04.2020 03:22
question
Mathematics, 15.04.2020 03:23
question
Mathematics, 15.04.2020 03:23
question
Mathematics, 15.04.2020 03:23
Questions on the website: 13722367