There are four steps in the manufacturing process of a stuffed toy: cutting, stuffing, sealing, and packaging. there are two employees each for cutting and stuffing but one each for sealing and packaging. the processing times of cutting, stuffing, sealing, and packaging are 8, 5, 3, and 2 seconds per toy. what is the bottleneck in the process? packaging stuffing sealing cutting

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:00
Upscale hotels in the united states recently cut their prices by 20 percent in an effort to bolster dwindling occupancy rates among business travelers. a survey performed by a major research organization indicated that businesses are wary of current economic conditions and are now resorting to electronic media, such as the internet and the telephone, to transact business. assume a company's budget permits it to spend $5,000 per month on either business travel or electronic media to transact business. graphically illustrate how a 20 percent decline in the price of business travel would impact this company's budget set if the price of business travel was initially $1,000 per trip and the price of electronic media was $500 per hour. suppose that, after the price of business travel drops, the company issues a report indicating that its marginal rate of substitution between electronic media and business travel is 1. is the company allocating resources efficiently? explain.
Answers: 1
question
Business, 21.06.2019 21:00
Following is a list of various costs incurred in producing replacement automobile parts. with respect to the production and sale of these auto parts, classify each cost as either variable costs, fixed costs, or mixed costs. 1. oil used in manufacturing equipment 2. plastic 3. property taxes, $165,000 per year on factory building and equipment 4. salary of plant manager 5. cost of labor for hourly workers 6. packaging 7. factory cleaning costs, $6,000 per month 8. metal 9. rent on warehouse, $10,000 per month plus $25 per square foot of storage used 10. property insurance premiums, $3,600 per month plus $0.01 for each dollar of property over $1,200,000 11. straight-line depreciation on the production equipment 12. hourly wages of machine operators 13. electricity costs, $0.20 per kilowatt-hour 14. computer chip (purchased from a vendor) 15. pension cost, $1.00 per employee hour on the job
Answers: 3
question
Business, 22.06.2019 09:40
Newton industries is considering a project and has developed the following estimates: unit sales = 4,800, price per unit = $67, variable cost per unit = $42, annual fixed costs = $11,900. the depreciation is $14,700 a year and the tax rate is 34 percent. what effect would an increase of $1 in the selling price have on the operating cash flow?
Answers: 2
question
Business, 22.06.2019 19:10
Imagine us is a startup that offers high definition 3d prenatal ultrasounds for high-end customers. the service process includes four activities that are conducted in the sequence described below. (the time required for each activity is shown in parentheses): activity 1: welcome a patient and explain the procedure. (20 minutes)activity 2: prep the patient (e.g., show them to the room, apply ultrasound gel). (17 minutes) (*your id number represents the amount of time needed to complete this task)activity 3: take images. (5 minutes)activity 4: discuss diagnostic with patient. (20 minutes)at each location there are employees (servers) s1, s2, and s3. the assignment of tasks to servers is the following: s1 does activities 1 and 2.s2 does activity 3.s3 does activity 4.a. what is the capacity of this process (in customers per hour)? b. suppose 3 patients arrive every hour on average. ignoring any β€œstart of day” or β€œend of day” effects, what are the utilizations of all three servers (%)? c. suppose each activity can be done by any server and any server can do any set of activities. however, each activity is done by only one server. for example, a possible assignment includes: s1 does activity 1, s2 does activity 2, and s3 does activities 3 and 4. of course, the original assignment of servers to activities is also feasible. what is the maximum capacity of the process (in customers per hour)? d. now consider the capacity measures in (c) and (a), what is the percentage change? why can you improve capacity without using additional resources? (there is no free lunch, right? )note: for all hw assignments, show your process of getting the results. only providing the final answers is not acceptable and will get 0%. if necessary, use a separate sheet of paper to show your work.
Answers: 3
You know the right answer?
There are four steps in the manufacturing process of a stuffed toy: cutting, stuffing, sealing, and...
Questions
question
Social Studies, 09.10.2021 08:00
question
Mathematics, 09.10.2021 08:00
Questions on the website: 13722363