Given the following information for a one-year project, answer the following questions. recall that pv is the planned value. ev is the earned value, ac is the actual cost, and bac is the budget at completion. pv = $23,000ev = $20,000ac = $25,000bac = $120,000a. what is the cost variance, schedule variance, cost performance index (cpi), and schedule performance index (spi) for the project? cost variance is calculated as ev-ac and indicates the difference between the budgeted cost and the actual cost of completed work. cost variance = ev-ac = $20,000 – $25,000 = - $ 5,000schedule variance is calculated as ev-pv and indicates the degree to which the value of completed work differs from that planned. schedule variance = ev-pv = $20,000 - $23,000 = -$ 3,000cost performance index (cpi) = ev/ac = 20,000/25,000 = 0.8 or 80%schedule performance index = ev/pv = 20,000 / 23,000 = 0.87 or 87%b. how is the project doing? is it ahead or schedule or behind schedule? is it under budget or over budget? the project is not doing well. because the cost variance and schedule variance are negative. a negative schedule variance means the project is behind schedule and a negative cost variance means the project is over cost. c. use the cpi to calculate the estimate at completion (eac) for this project. is the project performing better or worse than planned? eac = bac/cpi = $ 120,000/.8 = $ 150,000the project is performing worse than planned because the new estimate is $150,000 which is $30,000 more than initial estimate. d. use the schedule performance index (spi) to estimate how long it will take to finish this project. estimated time to complete = time estimate / spi = 12 months / .87 = 13.8the project is projected to take 13.8 months to complete so it is estimated that it will take 1.8 months more than planned. e. sketch the earned value chart based for this project (this is what i need )

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 19:20
Nominal gross domestic producta. is a measure of the overall level of pricesb. measures the value of final goods and services produced within the borders of a given country during a given time period using current pricesc. measures the value of final goods and services produced within the borders of a given country during a given time period corrected for changing pricesd. only changes when the level of output changes
Answers: 2
question
Business, 21.06.2019 20:50
Suppose the price of frozen yogurt, a substitute for ice cream, increases. what happens to equilibrium price and quantity of ice cream? a. the price and quantity of ice cream both increase b. the price and quantity of ice cream both decrease c. the price of ice cream increases and the quantity decreases d. the price of ice cream decreases and the quantity increases
Answers: 3
question
Business, 22.06.2019 00:50
Suppose that: 1. malaysia requires 1 hour of labor to produce 1 pound of rice and 2 hours of labor to produce 1 pencil; 2. indonesia requires 2 hours of labor to produce 1 pound of rice and 4 hours of labor to produce 1 pencil; 3. each country has 10,000 hours of labor to allocate between the production of rice and pencils; and 4. in autarky, malaysia consumes 5,000 pounds of rice and 2,500 pencils. which country has an absolute advantage in rice production? in pencil production? which country has a comparative advantage in rice production? in pencil production? will trade between the two countries be mutually beneficial?
Answers: 1
question
Business, 22.06.2019 18:00
Interpreting the income tax expense footnote the income tax footnote to the financial statements of fedex corporation follows. the components of the provision for income taxes for the years ended may 31 were as follows: ($ millions) 2010 2009 2008 current provision domestic federal $ 36 $ (35) $ 514 state and local 54 18 74 foreign 207 214 242 297 197 830 deferred provisions (benefit) domestic federal 408 327 31 state and local 15 48 (2) foreign (10) 7 32 413 382 61 provision for income taxes $ 710 $ 579 $ 891 (a)what is the amount of income tax expense reported in fedex's 2010, 2009, and 2008 income statements?
Answers: 2
You know the right answer?
Given the following information for a one-year project, answer the following questions. recall that...
Questions
question
Mathematics, 26.10.2020 09:40
question
English, 26.10.2020 09:40
question
Biology, 26.10.2020 09:40
Questions on the website: 13722363