In an mrp problem, a is an mps item. every a requires 3 b’s and 2 c’s. every b requires 5 c’s. all lead times are one period. initial inventory values for all items are 0. use lot-4-lot method for order quantities for all items. if gross requirement for a is 400 in period 10, what will be the planned order release for c in period 8?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 04:10
Universal containers(us) has an integration with its accounting system that creates tens of thousands of orders inside salesforce in a nightly batch. us wants to add automation that can attempt to match leads and contacts to these orders using the email address field on the insert. us is concerned about the performance of the automation with a large data volume. which tool should uc use to automate this process?
Answers: 1
question
Business, 22.06.2019 08:00
How do communism and socialism differ in terms of the role that government plays in the economy ?
Answers: 1
question
Business, 22.06.2019 13:40
Determine if the following statements are true or false. an increase in government spending can crowd out private investment. an improvement in the budget balance increases the demand for financial capital. an increase in private consumption may crowd out private investment. lower interest rates can lead to private investment being crowded out. a trade balance in sur+ increases the supply of financial capital. if private savings is equal to private investment, then there is neither a budget sur+ nor a budget deficit.
Answers: 1
question
Business, 22.06.2019 16:10
The following are line items from the horizontal analysis of an income statement:increase/ (decrease) increase/ (decrease) 2017 2016 amount percent fees earned $120,000 $100,000 $20,000 20% wages expense 50,000 40,000 10,000 25 supplies expense 2,000 1,700 300 15 which of the items is stated incorrectly? a. fees earned b. supplies expense c. none of these choices are correct. d. wages expense
Answers: 3
You know the right answer?
In an mrp problem, a is an mps item. every a requires 3 b’s and 2 c’s. every b requires 5 c’s. all l...
Questions
question
Mathematics, 15.10.2019 19:00
Questions on the website: 13722367