Mountain ski corp. was set up to take large risks and is willing to take the greatest risk possible. lakeway train co. is more typical of the average corporation and is risk-averse.
returns:
projects expected value standard deviation
a $ 298,000 $ 210,000
b 704,000 454,000
c 164,000 133,000
d 196,000 252,000
a-1. compute the coefficients of variation.
a-2. which projects should mountain ski corp. choose?
b. which one of the four projects should lakeway train co. choose based on the same criteria of using the coefficient of variation?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 17:30
Gary lives in an area that receives high rainfall and thunderstorms throughout the year. which device would be useful to him to maintain his computer?
Answers: 2
question
Business, 24.06.2019 01:30
Dr. ezekiel found a correlation of 0.73 between scores on a measure of physical exercise and pounds lost in a diet program in a sample of men over 40. this correlation coefficient indicates that:
Answers: 3
question
Business, 24.06.2019 03:50
What has the greatest potential to demotivate you and lead you to unproductive activities? goals that are difficult to achieve multiple goals within a short-term period goals that are the same as other people’s goals restructuring a long-term goal
Answers: 3
question
Business, 24.06.2019 11:00
Which office 365 feature keeps exchange, lync, and sharepoint up to date?
Answers: 1
You know the right answer?
Mountain ski corp. was set up to take large risks and is willing to take the greatest risk possible....
Questions
question
Chemistry, 08.04.2020 02:13
question
Mathematics, 08.04.2020 02:13
Questions on the website: 13722367