Consider the following work breakdown structure:
time estimates (days)
activity precedes optimistic most likely pessimistic
start a, b, c - - -
a d 38 50 62
b e 90 99 108
c end 85 100 115
d f 19 25 31
e end 91 100 115
f end 62 65 68
what is the estimated expected (mean) time for project completion?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:30
How do primary and secondary industries differ
Answers: 1
question
Business, 21.06.2019 21:00
Sheldon has the following year-end account balances: accounts receivable, $5,000; supplies, $12,000; equipment, $18,000; accounts payable, $17,000; stockholders’ equity, $43,000. the cash account balance was not available at year-end. given the account balances listed, the balance in the cash account should be?
Answers: 2
question
Business, 22.06.2019 09:30
Stock market crashes happen when the value of most of the stocks in the stock market increase at the same time. question 10 options: true false
Answers: 1
question
Business, 22.06.2019 12:30
Consider a treasury bill with a rate of return of 5% and the following risky securities: security a: e(r) = .15; variance = .0400 security b: e(r) = .10; variance = .0225 security c: e(r) = .12; variance = .1000 security d: e(r) = .13; variance = .0625 the investor must develop a complete portfolio by combining the risk-free asset with one of the securities mentioned above. the security the investor should choose as part of her complete portfolio to achieve the best cal would be a. security a b. security b c. security c d. security d
Answers: 3
You know the right answer?
Consider the following work breakdown structure:
time estimates (days)
activity prece...
Questions
question
English, 22.10.2020 20:01
question
Mathematics, 22.10.2020 20:01
question
Law, 22.10.2020 20:01
question
Mathematics, 22.10.2020 20:01
question
Mathematics, 22.10.2020 20:01
Questions on the website: 13722361