Which of the following steps is not a basic step followed by pert and cpm?
a. compute the critical path.
b. draw the network connecting all the activities.
c. define the project.
d. identify and eliminate non-critical activities.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:30
On january 1, 2018, jay company acquired all the outstanding ownership shares of zee company. in assessing zee's acquisition-date fair values, jay concluded that the carrying value of zee's long-term debt (8-year remaining life) was less than its fair value by $21,600. at december 31, 2018, zee company's accounts show interest expense of $14,440 and long-term debt of $380,000. what amounts of interest expense and long-term debt should appear on the december 31, 2018, consolidated financial statements of jay and its subsidiary zee? long-term debt $401,600 $398,900 $401,600 $398,900 interest expense $17,140 $17,140 $11,740 $11,740 a. b. c. d.
Answers: 3
question
Business, 22.06.2019 15:20
Abank has $132,000 in excess reserves and the required reserve ratio is 11 percent. this means the bank could have in checkable deposit liabilities and in (total) reserves.
Answers: 3
question
Business, 23.06.2019 00:30
In a recent annual report, apple computer reported the following in one of its disclosure notes: "warranty expense: the company provides currently for the estimated cost for product warranties at the time the related revenue is recognized." this note exemplifies apple's use of: (a) conservatism.(b) matching. (c) realization principle. (d) economic entity.
Answers: 2
question
Business, 23.06.2019 01:40
Which of the following statements is incorrect? select one: a. personal creditors have first claim on partnership assets.b. partnerships are subject to dual taxation.c. no law requires partners to create a written partnership agreement, but it's smart to do so.d. partnership has limited life and unlimited liability.
Answers: 3
You know the right answer?
Which of the following steps is not a basic step followed by pert and cpm?
a. compute the cr...
Questions
question
Mathematics, 22.04.2021 07:30
question
Mathematics, 22.04.2021 07:40
question
Mathematics, 22.04.2021 07:40
question
Mathematics, 22.04.2021 07:40
question
Mathematics, 22.04.2021 07:40
Questions on the website: 13722360