Given the following information about a small project, task duration immediateestimates predecessorsa 2 days noneb 5 days ac 4 days bd 9 days ae 4 days b & df 12 days e & cdraw a network diagram. identify the critical path, earliest start and finish and slack for each task. using ms excel, produce a gantt chart for this project. what would happen if a new estimate for task d increases its expected duration from 9 days to 11 days? would the project take longer? would anything else change?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 13:30
Jose recently died with a probate estate of $900,000. he was predeceased by his wife, guadalupe, and his daughter, lucy. he has two surviving children, pete and fred. jose was also survived by eight grandchildren, pete’s three children, naomi, daniel, nick; fred’s three children, heather, chris and steve; and lucy’s two children, david and rachel. jose’s will states the following “i leave everything to my three children. if any of my children shall predecease me then i leave their share to their heirs, per stirpes.” which of the following statements is correct? (a) under jose’s will rachel will receive $150,000. (b) under jose’s will chris will receive $150,000. (c) under jose’s will nick will receive $100,000. (d) under jose’s will pete will receive $200,000.
Answers: 1
question
Business, 23.06.2019 00:50
Hubert manages a grocery store in a country experiencing a high rate of inflation. to keep up with inflation, he spends a lot of time every day updating the prices, printing new price tags, and sending out newspaper inserts advertising the new prices. his employees regularly deal with customer annoyance over the frequent price changes. this is an example of the of inflation.
Answers: 2
question
Business, 23.06.2019 01:00
Sarah is an accountant with desires to open her own business. she is looking for office space at a reasonable rate along with internet service. of the conditions that need to be put in place for the entrepreneurial ecosystem, she needs
Answers: 1
question
Business, 23.06.2019 02:10
Make or buy eastside company incurs a total cost of $120,000 in producing 10,000 units of a component needed in the assembly of its major product. the component can be purchased from an outside supplier for $11 per unit. a related cost study indicates that the total cost of the component includes fixed costs equal to 50% of the variable costs involved. a. should eastside buy the component if it cannot otherwise use the released capacity? present your answer in the form of differential analysis. use negative sign represent a net disadvantage answer; otherwise do not use negative signs with your answers. cost from outside supplier $answer variable costs avoided by purchasing answer net advantage (disadvantage) to purchase alternative $answer b. what would be your answer to requirement (a) if the released capacity could be used in a project that would generate $50,000 of contribution margin? use negative sign represent a net disadvantage answer; otherwise do not use negative signs with your answers.
Answers: 2
You know the right answer?
Given the following information about a small project, task duration immediateestimates predecessors...
Questions
Questions on the website: 13722359