Wateredge corporation has budgeted a total of $361,800 in costs and expenses for the upcoming quarter. of this amount, $45,000 represents depreciation expense and $7,300 represents the expiration of prepayments. wateredge's current payables balance is $265,000 at the beginning of the quarter. budgeted payments on current payables for the quarter amount to $370,000. the company's estimated current payables balance at the end of the quarter is:

(a) $179,500.
(b) $204,500.
(c) $203,500.
(d) $310,000.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:50
Which of the following is the most important role of marketing in the process selection decision? identifying points of differentiation for mass customization. stimulating demand in developing markets. estimating and managing future demand. providing translation of the voice of the customer.
Answers: 2
question
Business, 22.06.2019 15:00
Oerstman, inc. uses a standard costing system and develops its overhead rates from the current annual budget.the budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours.(practical capacity is 500,000 hours)annual budgeted overhead costs total $772,800, of which $556,800 is fixed overhead.a total of 119,300 units, using 478,000 direct labor hours, were produced during the year.actual variable overhead costs for the year were $260,400 and actual fixed overhead costs were $555,450.required: 1. compute the fixed overhead spending variance and indicate if favorable or unfavorable.2. compute the fixed overhead volume variance and indicate if favorable or unfavorable.
Answers: 3
question
Business, 22.06.2019 17:00
Dan wants to start a supermarket in his hometown, and wants to get into the business only after finding out about the market and how successful his business might be. the best way for dan to gain knowledge is to:
Answers: 2
question
Business, 23.06.2019 00:00
In this multi-channel funnel report, which two channels have the highest overlap and would benefit from coordinated marketing messaging?
Answers: 2
You know the right answer?
Wateredge corporation has budgeted a total of $361,800 in costs and expenses for the upcoming quarte...
Questions
question
Mathematics, 05.02.2021 21:50
question
Mathematics, 05.02.2021 21:50
question
Social Studies, 05.02.2021 21:50
question
Mathematics, 05.02.2021 21:50
question
Mathematics, 05.02.2021 21:50
question
Mathematics, 05.02.2021 21:50
Questions on the website: 13722359