Aproject is composed of the following activities: immediate activity predecessor days a — 4 b — 9 c a 3 d b 8 e b 7 f d 2 g e 5 (a) draw the project network and compute the earliest start, latest start, earliest finish, and latest finish time for each activity. (b) how long will it take to complete the project? (c) what is the critical path? (d) compute the slack for each of the non-critical activities. (e) if activity a were to be delayed and takes three days longer than planned, by how much would the project be delayed? (f) if the time to complete activity b were to be reduced by one day, how much sooner would the project be completed? (g) if the time to complete activity e were to be reduced by three days, how much sooner would the project be completed?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 22:50
The leading producer of cell phone backup batteries, jumpstart, has achieved great success because they produce high-quality battery backups that are not too expensive. even so, another company that produces lower-quality batteries at the same price has also achieved some success, but not as much as jumpstart. also, in general, the price of backup batteries has declined because of economies of scale and learning. in addition, jumpstart has added complementary assets, such as a carrying case. considering all of these factors, the backup battery industry is most likely in the introduction stage. growth stage. shakeout stage. maturity stage.
Answers: 2
question
Business, 22.06.2019 10:00
You are president of a large corporation. at a typical monthly meeting, each of your vice presidents gives standard area reports. in the past, these reports have been good, and the vps seem satisfied about their work. based on situational approach to leadership, which leadership style should you exhibit at the next meeting?
Answers: 2
question
Business, 22.06.2019 17:30
What is the sequence of events that could lead to trade surplus
Answers: 3
question
Business, 22.06.2019 22:00
What legislation increased the ability for federal authorities to tap telephones and wireless devices, tightened the enforcement of money laundering activities, as well as broadened powers toward acts of terrorism and acts such as drug trafficking?
Answers: 2
You know the right answer?
Aproject is composed of the following activities: immediate activity predecessor days a — 4 b — 9 c...
Questions
question
English, 30.03.2020 22:28
question
Mathematics, 30.03.2020 22:29
Questions on the website: 13722361