Athird method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost. if the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then
a. the fcac is less than the tbc.
b. the fcac is greater than the tbc.
c. the fcac cannot be calculated with the values given.
d. additional information is needed to predict the fcac.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:30
Copyright law protects the expression of an idea so blank is protected by copyright
Answers: 1
question
Business, 22.06.2019 19:00
All of the following led to the collapse of the soviet economy except a. a lack of worker incentives. c. inadequate supply of consumer goods. b. a reliance on production quotas. d. the introduction of a market economy.
Answers: 1
question
Business, 22.06.2019 20:00
Double corporation acquired all of the common stock of simple company for
Answers: 1
question
Business, 22.06.2019 22:30
Suppose that each country completely specializes in the production of the good in which it has a comparative advantage, producing only that good. in this case, the country that produces jeans will produce million pairs per week, and the country that produces corn will produce million bushels per week.
Answers: 1
You know the right answer?
Athird method for determining the forecasted cost at completion is to re-estimate the costs for all...
Questions
question
Mathematics, 21.12.2020 06:30
question
History, 21.12.2020 06:30
question
Computers and Technology, 21.12.2020 06:30
question
Mathematics, 21.12.2020 06:30
Questions on the website: 13722359