Business, 25.11.2019 19:31 shaeby13

Acompany works 320 days per year and has an annual demand of 2080 units of product desires to set an reorder point that will cover demand during lead time. if the lead time is 4 working days, what should the reorder point be? group of answer choices

6.5 units
14 units
20 units
26 units
160 units

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:40
Which of the following actions is most likely to result in a decrease in the money supply? a. the discount rate on overnight loans is lowered. b. the government sells a new batch of treasury bonds. c. the federal reserve bank buys treasury bonds. d. the required reserve ratio for banks is decreased. 2b2t
Answers: 2
question
Business, 22.06.2019 17:30
Which of the following services will be provided by a full-service broker but not by a discount broker? i. research of potential investment opportunities ii. purchase and sale of stock at your request iii. recommendation of investments a. i and iii b. ii only c. iii only d. i, ii, and ii
Answers: 2
question
Business, 22.06.2019 22:00
Only the united states has embassies. true or false
Answers: 2
question
Business, 23.06.2019 00:30
Industrial engineers who specialize in ergonomics are concerned with designing workspace and devices operated by workers so as to achieve high productivity and comfort. a paper published in this research area reports on a study of preferred height for an experimental keyboard with large forearm-wrist support. a sample of 31 trained typists resulted in an average preferred height of 80.0 cm
Answers: 1
You know the right answer?
Acompany works 320 days per year and has an annual demand of 2080 units of product desires to set an...
Questions
question
Chemistry, 10.11.2020 17:20
question
Mathematics, 10.11.2020 17:20
Questions on the website: 13722361