You manage a project with 10 activities. activities a1, a3, a5, a9 form the critical path. as you have a large budget for the project, you are considering crashing activity a2, which has the potential to shorten the time of a2 by 3 days.
what do you think about this opportunity?
o a good idea, it will reduce the project duration by 3 days.
o a bad idea, as a2 is not on the critical path.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 15:00
Beagle autos is known for its affordable and reliable brand of consumer vehicles. because its shareholders expect to see an improved rate of growth in the coming years, beagle's executives have decided to diversify the company's range of products so that at least 40 percent of the firm's revenue is generated by new business units. however, the company's resources, capabilities, and competencies are limited to producing other forms of motorized vehicles, such as motorcycles and all-terrain vehicles (atvs). which type of corporate diversification strategy should beagle pursue?
Answers: 1
question
Business, 22.06.2019 17:20
“strategy, plans, and budgets are unrelated to one another.” do you agree? explain. explain how the manager’s choice of the type of responsibility center (cost, revenue, profit, or investment) affects the behavior of other employees.
Answers: 3
question
Business, 23.06.2019 03:00
What are the uses of national income data
Answers: 1
question
Business, 23.06.2019 17:00
Select each of the paced steps below. define the problem. conduct an internet search for information. list the alternatives. select the criteria. evaluate the alternatives. make a decision. evaluate the decision.
Answers: 3
You know the right answer?
You manage a project with 10 activities. activities a1, a3, a5, a9 form the critical path. as you ha...
Questions
question
Biology, 18.12.2019 15:31
question
Physics, 18.12.2019 15:31
question
Mathematics, 18.12.2019 15:31
Questions on the website: 13722363