Horner construction co. uses the percentage-of-completion method. in 2014, horner began work on a contract for $16,500,000; it was completed in 2015. the following cost data pertain to this contract :
year ended december 31
2014 2015
costs incurred during the year $5,850,000 $4,200,000
estimated costs to complete at the end of year 3,900,000 —
if the completed-contract method of accounting was used, the amount of gross profit to be recognized for years 2014 and 2015 would be

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 10:50
You are evaluating two different silicon wafer milling machines. the techron i costs $285,000, has a three-year life, and has pretax operating costs of $78,000 per year. the techron ii costs $495,000, has a five-year life, and has pretax operating costs of $45,000 per year. for both milling machines, use straight-line depreciation to zero over the project’s life and assume a salvage value of $55,000. if your tax rate is 24 percent and your discount rate is 11 percent, compute the eac for both machines.
Answers: 3
question
Business, 23.06.2019 01:00
Jimmy's delicatessen sells large tins of tom tucker's toffee. the deli uses a periodic review system, checking inventory levels every 88 days, at which time an order is placed for more tins. order lead time is 22 days. daily demand is a constant 1515 tins, so average demand during the reorder period and order lead time (1010 days) is 150150 tins. draw a sawtooth diagram. assume that the beginning inventory level is equal to the restocking level and the desired service level is 99.9%. what is the safety stock level? (hint: look at the formula for calculating restocking level.) what is the average inventory level? the safety stock level is average inventory level is __chart: time (10,20,30), tins (0,150) lines touching both axisthe safety stock level is 0 tinsthe average inventory level is 75 tins
Answers: 2
question
Business, 23.06.2019 07:50
How do you know if two line segments are perpendicular?
Answers: 1
question
Business, 23.06.2019 14:30
Gather reliable information to brent make his decision. to gather this information, use newspapers, call insurance companies or look at their web sites, and review consumer magazines and web sites. also, look at the manufacturer web site or for information about gas mileage. list the sources you use and take notes.
Answers: 2
You know the right answer?
Horner construction co. uses the percentage-of-completion method. in 2014, horner began work on a co...
Questions
question
History, 13.07.2019 13:30
question
Mathematics, 13.07.2019 13:30
question
Physics, 13.07.2019 13:30
question
Mathematics, 13.07.2019 13:30
question
Mathematics, 13.07.2019 13:30
question
Mathematics, 13.07.2019 13:30
question
Mathematics, 13.07.2019 13:30
Questions on the website: 13722367