L1: it takes 32,355 hours to produce the sixth ship of the lpd class at a shipyard. the learning curve rate is 85%. how long does it take to produce the seventh ship?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:00
Which statement is true of both presidential and parliamentary systems of government? a. the executive branch operates independently from the legislative branch. b. the members of the legislative branch are directly elected by the people. c. the head of government is chosen by members of his or her political party. d. the head of government is directly elected by the people
Answers: 1
question
Business, 22.06.2019 04:40
Select the correct text in the passage.which sentences in the given passage explains the limitations of monetary policies? monetary policies - limitationsmonetary policies are set by the central bank to bring about growth in the economy.de can be achieved these policiesw at anden i sca poit would be fair to say that changes in the economy cannot be brought about instantly by monetary po des.monetary policy can only influence not control, economic growththe monetary policy makers do work on sining the perfect balance between demand and supply of money in the economy
Answers: 3
question
Business, 22.06.2019 16:00
In microeconomics, the point at which supply and demand meet is called the blank price
Answers: 3
question
Business, 22.06.2019 17:10
To : of $25 up to 35 2 35 up to 45 5 45 up to 55 7 55 up to 65 20 65 up to 75 16 is$25 up to $35 ?
Answers: 1
You know the right answer?
L1: it takes 32,355 hours to produce the sixth ship of the lpd class at a shipyard. the learning cu...
Questions
question
Mathematics, 12.02.2022 09:50
question
Physics, 12.02.2022 09:50
Questions on the website: 13722363