subject
Business, 10.12.2019 03:31 rasv4799

Activities a, b, and c are part of the same project. activity a is worth $200, is 100% complete, and actually cost $200. activity b is worth $75, is 90% complete, and actual cost $120 so far. activity c is worth $200, is 75% complete, and has cost $175 so far. the total budget is $1,000. what is the cost variance (cv) for the project

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:50
Demand increases by less than supply increases. as a result, (a) equilibrium price will decline and equilibrium quantity will rise. (b) both equilibrium price and quantity will decline. (c) both equilibrium price and quantity will rise
Answers: 3
question
Business, 22.06.2019 16:50
Slow ride corp. is evaluating a project with the following cash flows: year cash flow 0 –$12,000 1 5,800 2 6,500 3 6,200 4 5,100 5 –4,300 the company uses a 11 percent discount rate and an 8 percent reinvestment rate on all of its projects. calculate the mirr of the project using all three methods using these interest rates.
Answers: 2
question
Business, 22.06.2019 22:20
As a result of a labeling mistake at the chemical factory, a farmer accidentally sprays weedkiller rather than fertilizer on half her land. as a result, she loses half of her productive farmland. if the property of diminishing returns applies to all factors of production, she should expect to seea. a decrease in the marginal productivity of her remaining land and an increase in the marginal productivity of her labor. b. an increase in the marginal productivity of her remaining land and an increase in the marginal productivity of her labor. c. an increase in the marginal productivity of her remaining land and a decrease in the marginal productivity of her labor. d. a decrease in the marginal productivity of her remaining land and a decrease in the marginal productivity of her labor.
Answers: 2
question
Business, 23.06.2019 05:30
Aslam wants to create multiple worksheet containing common formatting styles for his team members. which file extension him to save these worksheets? [templates,workbooks,files] aslam to create multiple worksheets with common styles. he needs to save them with the [xlsb,xlts,xls,xlsm] extension.
Answers: 2
You know the right answer?
Activities a, b, and c are part of the same project. activity a is worth $200, is 100% complete, and...
Questions
question
English, 25.01.2021 19:10
question
Mathematics, 25.01.2021 19:10
Questions on the website: 13722367