In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the: multiple choice: o mean time. o marginal time. o mode time. o most likely time. o median time.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 12:30
Amap from a trade development commission or chamber of commerce can be more useful than google maps for identifying
Answers: 1
question
Business, 22.06.2019 17:30
If springfield is operating at full employment who is working a. everyone b. about 96% of the workforce c. the entire work force d. the robots
Answers: 1
question
Business, 22.06.2019 17:40
Slimwood corporation made sales of $ 725 million during 2018. of this amount, slimwood collected cash for $ 670 million. the company's cost of goods sold was $ 300 million, and all other expenses for the year totaled $ 400 million. also during 2018, slimwood paid $ 420 million for its inventory and $ 285 million for everything else. beginning cash was $ 110 million. carter's top management is interviewing you for a job and they ask two questions: (a) how much was carter's net income for 2018? (b) how much was carter's cash balance at the end of 2016? you will get the job only if you answer both questions correctly.
Answers: 1
question
Business, 22.06.2019 18:00
1. what is the amount of interest earned after two years on a $100 deposit paying 4 percent simple interest annually? $8.00 $4.08 $8.16 $4.00 2. what is the amount of compound interest earned after three years on a $100 deposit paying 8 percent interest annually? $24.00 $8.00 $16.64 $25.97 3. a business just took out a loan for $100,000 at 10% interest. if the business pays the loan off in three months, how much did the business pay in interest? $2,500.00 $10.00 $250.00 $10,000.00 4. what is the annual percentage yield (apy) for a deposit paying 5 percent interest with monthly compounding? 5.00% 5.12% 79.59% 0.42%
Answers: 1
You know the right answer?
In the probabilistic approach to project network analysis, the time estimate annotated tm for any ac...
Questions
Questions on the website: 13722367