Business, 28.12.2019 02:31 FoxGirl1971

Transmissions are delivered to the fabrication line five at a time. it takes two hours for transmissions to be delivered. approximately three vehicles are produced each hour, and management has decided that 30 percent of expected demand should be maintained as safety stock. how many kanban card sets are needed? (round up your answer to the next whole number.)

number of kanban card sets

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:30
The distinction between a normal and an inferior good is
Answers: 3
question
Business, 23.06.2019 02:30
Complete electronics inc. sells a point-of-sale computer with a two-year service contract. complete collects $ 2 comma 500 cash for the selling price of the computer and $ 576 for the two-year service contract. how is revenue recognized?
Answers: 2
question
Business, 23.06.2019 05:10
To use google as main search engine, which internet browser can i use
Answers: 2
question
Business, 23.06.2019 09:00
The average cost of one year at a private college in 2012-2013 is $43,289. the average grant aid received by a student at a private college in 2012-2013 is $15,680.what is the average student contribution for one year at a private college in 2012-2013?
Answers: 2
You know the right answer?
Transmissions are delivered to the fabrication line five at a time. it takes two hours for transmiss...
Questions
question
Mathematics, 27.03.2020 09:58
question
Mathematics, 27.03.2020 09:58
question
Mathematics, 27.03.2020 09:58
Questions on the website: 13722360