If a, b, and c are three activities connected with ss and ff (combination) relationships with no lags, their durations are 5, 10, and 3; respectively. what is the duration of the project?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 17:00
The risk-free rate is 7% and the expected rate of return on the market portfolio is 11%. a. calculate the required rate of return on a security with a beta of 1.92. (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.) b. if the security is expected to return 15%, is it overpriced or underpriced?
Answers: 2
question
Business, 21.06.2019 23:00
Assume today is december 31, 2013. barrington industries expects that its 2014 after-tax operating income [ebit(1 Γ’β‚¬β€œ t)] will be $400 million and its 2014 depreciation expense will be $70 million. barrington's 2014 gross capital expenditures are expected to be $120 million and the change in its net operating working capital for 2014 will be $25 million. the firm's free cash flow is expected to grow at a constant rate of 4.5% annually. assume that its free cash flow occurs at the end of each year. the firm's weighted average cost of capital is 8.6%; the market value of the company's debt is $2.15 billion; and the company has 180 million shares of common stock outstanding. the firm has no preferred stock on its balance sheet and has no plans to use it for future capital budgeting projects. using the corporate valuation model, what should be the company's stock price today (december 31, 2013)? round your answer to the nearest cent. do not round intermediate calculations.
Answers: 1
question
Business, 22.06.2019 00:30
Find the interest rate for a $4000 deposit accumulating to $5234.58, compounded quarterly for 9 years
Answers: 1
question
Business, 22.06.2019 05:00
Identify an organization with the low-total-cost value proposition and suggest at least two possible measures within each of the four balanced scorecard perspectives.
Answers: 3
You know the right answer?
If a, b, and c are three activities connected with ss and ff (combination) relationships with no lag...
Questions
Questions on the website: 13722361