If the person completing a project activity will be repeating the activity later in the project, the effect of learning curves should be considered when estimating what?
a) one-point estimates
b) future durations
c) learning curves
d) beta distributions

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 15:00
Abroker showed one of his own listings to a buyer he was representing. the buyer decided to make an offer on the property, which was accepted. at no point did the broker disclose his dual agency status. the broker may be:
Answers: 3
question
Business, 22.06.2019 05:00
Xie company identified the following activities, costs, and activity drivers for 2017. the company manufactures two types of go-karts: deluxe and basic. activity expected costs expected activity handling materials $ 625,000 100,000 parts inspecting product 900,000 1,500 batches processing purchase orders 105,000 700 orders paying suppliers 175,000 500 invoices insuring the factory 300,000 40,000 square feet designing packaging 75,000 2 models required: 1. compute a single plantwide overhead rate, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours. 2. in january 2017, the deluxe model required 2,500 direct labor hours and the basic model required 6,000 direct labor hours. assign overhead costs to each model using the single plantwide overhead rate.
Answers: 3
question
Business, 22.06.2019 10:20
Sye chase started and operated a small family architectural firm in 2016. the firm was affected by two events: (1) chase provided $25,000 of services on account, and (2) he purchased $2,800 of supplies on account. there were $250 of supplies on hand as of december 31, 2016. record the two transactions in the accounts. record the required year-end adjusting entry to reflect the use of supplies and the required closing entries. post the entries in the t-accounts and prepare a post-closing trial balance.
Answers: 1
question
Business, 22.06.2019 22:00
Which of the following is a function performed by market prices? a. market prices communicate information to buyers and sellers. b. market prices coordinate the decisions of buyers and sellers. c. market prices motivate entrepreneurs to produce those products that are currently most desired relative to their costs of production. d. all of the above are functions performed by market prices.
Answers: 2
You know the right answer?
If the person completing a project activity will be repeating the activity later in the project, the...
Questions
question
Biology, 28.08.2019 03:30
Questions on the website: 13722361