Business, 17.01.2020 19:31 naenae1405

The local driver’s license center processes applications for driver’s license renewals through the following three steps. first, the customer registers with the receptionist, who updates the customer’s information in the database. this first step takes 2 minutes per customer. then the customer visits one of two cashiers to pay the associated fees for the license renewal. this takes 8 minutes per customer because several forms must be printed from the computer and signed by the customer. finally, the customer visits one of three license processing stations where the customer’s picture is taken and the license is printed. this final step takes 15 minutes per customer.

a. assuming unlimited demand, what is the flow rate of the process in customers per hour? per hour
b. assuming unlimited demand, what would the new flow rate be if the center added one server to the bottleneck resource? per hour

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 18:30
What’s the best type of healthcare plan
Answers: 1
question
Business, 21.06.2019 23:00
Each of the four independent situations below describes a sales-type lease in which annual lease payments of $12,500 are payable at the beginning of each year. each is a finance lease for the lessee. (fv of $1, pv of $1, fva of $1, pva of $1, fvad of $1 and pvad of $1) (use appropriate factor(s) from the tables provided.) situation 1 2 3 4 lease term (years) 3 3 3 3 asset’s useful life (years) 3 4 4 6 lessor’s implicit rate (known by lessee) 14 % 14 % 14 % 14 % residual value: guaranteed by lessee 0 $ 5,000 $ 2,500 0 unguaranteed 0 0 $ 2,500 $ 5,000 purchase option: after (years) none 2 3 3 exercise price n/a $ 7,500 $ 1,500 $ 3,500 reasonably certain? n/a no no yes
Answers: 1
question
Business, 22.06.2019 07:10
mark, a civil engineer, entered into a contract with david. as per the contract, mark agreed to design and build a house for david for a specified fee. mark provided david with an estimation of the total cost and the contract was mutually agreed upon. however, during construction, when mark increased the price due to a miscalculation on his part, david refused to pay the amount. this scenario is an example of a mistake.
Answers: 1
question
Business, 22.06.2019 10:30
On july 1, oura corp. made a sale of $ 450,000 to stratus, inc. on account. terms of the sale were 2/10, n/30. stratus makes payment on july 9. oura uses the net method when accounting for sales discounts. ignore cost of goods sold and the reduction of inventory. a. prepare all oura's journal entries. b. what net sales does oura report?
Answers: 2
You know the right answer?
The local driver’s license center processes applications for driver’s license renewals through the f...
Questions
question
Mathematics, 10.07.2019 09:20
question
Mathematics, 10.07.2019 09:20
question
Mathematics, 10.07.2019 09:20
Questions on the website: 13722359