Why is the critical path critical?
a. any delay in the critical path delays the project finish date.
b. it represents tasks in which resources are overallocated.
c. it represents tasks that are delayed.
d. the tasks on the critical path are the most important ones for achieving the project goal.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 17:30
Which of the following best describes biochemical evidence that would not support the modern concept of evolution? a. a bacterium that uses inorganic materials to produce energy b. an organism that does not undergo cellular respiration c. a species of bacteria that is capable of photosynthesis d. an organism that undergoes both aerobic and anaerobic respiration
Answers: 2
question
Business, 22.06.2019 14:40
You are purchasing a bond that currently sold for $985.63. it has the time-to-maturity of 10 years and a coupon rate of 6%, paid semi-annually. the bond can be called for $1,020 in 3 years. what is the yield to maturity of this bond?
Answers: 2
question
Business, 22.06.2019 23:30
Which statement best describes entrepreneurship aitmakes people very rich b it relies on large financial investments c it is only possible in the retail industry d it requires creativity and ambition
Answers: 3
question
Business, 23.06.2019 02:00
In his speech on varying explanations of how the earth came into existence, eduardo begins with opinions, moves to inferences, and uses scientific facts in support of his last point. what principle of supporting material organization is eduardo utilizing in his speech?
Answers: 3
You know the right answer?
Why is the critical path critical?
a. any delay in the critical path delays the project finis...
Questions
question
Social Studies, 16.10.2020 08:01
question
Mathematics, 16.10.2020 08:01
question
History, 16.10.2020 08:01
question
Mathematics, 16.10.2020 08:01
Questions on the website: 13722360