Pearl products limited of shenzhen, china, manufactures and distributes toys throughout south east asia. three cubic centimeters (cc) of solvent h300 are required to manufacture each unit of supermix, one of the company’s products. the company is now planning raw materials needs for the third quarter, the quarter in which peak sales of supermix occur. to keep production and sales moving smoothly, the company has the following inventory requirements:

a.
the finished goods inventory on hand at the end of each month must be equal to 4,000 units of supermix plus 25% of the next month’s sales. the finished goods inventory on june 30 is budgeted to be 21,250 units.

b.
the raw materials inventory on hand at the end of each month must be equal to one-half of the following month’s production needs for raw materials. the raw materials inventory on june 30 is budgeted to be 88,000 cc of solvent h300.

c. the company maintains no work in process inventories.
a sales budget for supermix for the last six months of the year follows.
budgeted sales
in units
july 69,000
august 74,000
september 84,000
october 64,000
november 54,000
december 44,000

required:

1.
prepare a production budget for supermix for the months july, august, september, and october.

2.
prepare a direct materials budget showing the quantity of solvent h300 to be purchased for july, august, and september, and for the quarter in total.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:00
What is the correct percentage of texas teachers charged with ethics violations each year?
Answers: 2
question
Business, 22.06.2019 17:00
Cadbury has a chocolate factory in dunedin, new zealand. for easter, it makes two kinds of “easter eggs”: milk chocolate and dark chocolate. it cycles between producing milk and dark chocolate eggs. the table below provides data on these two products. demand (lbs per hour) milk: 500 dark: 200 switchover time (minutes) milk: 60 dark: 30 production rate per hour milk: 800 dark: 800 for example, it takes 30 minutes to switch production from milk to dark chocolate. demand for milk chocolate is higher (500lbs per hour versus 200 lbs per hour), but the line produces them at the same rate (when operating): 800 lbs per hour. a : suppose cadbury produces 2,334lbs milk chocolate and 1,652 lbs of dark chocolate in each cycle. what would be the maximum inventory (lbs) of milk chocolate? b : how many lbs of milk and dark chocolate should be produced with each cycle so as to satisfy demand while minimizing inventory?
Answers: 2
question
Business, 22.06.2019 20:50
Lead time for one of your fastest-moving products is 20 days. demand during this period averages 90 units per day.a) what would be an appropriate reorder point? ) how does your answer change if demand during lead time doubles? ) how does your answer change if demand during lead time drops in half?
Answers: 1
question
Business, 22.06.2019 22:40
Which of the following will not cause the consumption schedule to shift? a) a sharp increase in the amount of wealth held by households b) a change in consumer incomes c) the expectation of a recession d) a growing expectation that consumer durables will be in short supply
Answers: 1
You know the right answer?
Pearl products limited of shenzhen, china, manufactures and distributes toys throughout south east a...
Questions
question
Mathematics, 29.11.2020 16:50
question
Mathematics, 29.11.2020 16:50
question
Social Studies, 29.11.2020 16:50
Questions on the website: 13722367