In order to avoid project delays, project managers confronted with a resource overload will seek to delay some of the noncritical activities by an amount no more than their slack period, to level the demand for that worker.
a. true
b. false

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 10:30
Factors like the unemployment rate, the stock market, global trade, economic policy, and the economic situation of other countries have no influence on the financial status of individuals. ( t or f)
Answers: 1
question
Business, 22.06.2019 10:30
How are interest rates calculated by financial institutions? financial institutions generally calculate interest as (1) interest or (.
Answers: 1
question
Business, 22.06.2019 16:30
Summarize the specific methods used by interest groups in order to influence governmental decisions making in all three branches of government. provide at least two examples from each branch.
Answers: 3
question
Business, 23.06.2019 02:00
Suppose that a major city’s main thoroughfare, which is also an interstate highway, will be completely closed to traffic for two years, from january 2014 to december 2015, for reconstruction at a cost of $535 million. if the construction company were to keep the highway open for traffic during construction, the highway reconstruction project would take much longer and be more expensive. suppose that construction would take four years if the highway were kept open, at a total cost of $800 million. the state department of transportation had to make its decision in 2014, one year before the start of construction (so that the first payment was one year away). so the department of transportation had the following choices: (i) close the highway during construction, at an annual cost of $267.5 million per year for two years. (ii) keep the highway open during construction, at an annual cost of $200 million per year for four years. now suppose the interest rate is 80%. calculate the present value of the costs incurred under each plan.
Answers: 3
You know the right answer?
In order to avoid project delays, project managers confronted with a resource overload will seek to...
Questions
question
Biology, 07.04.2021 18:30
question
World Languages, 07.04.2021 18:40
question
Physics, 07.04.2021 18:40
question
Mathematics, 07.04.2021 18:40
Questions on the website: 13722359