Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have (25/30) percent of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, and cost (actually revenue in this case) variance and cost (actually revenue here) performance index. How is the project going?
Hint:Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 05:10
Suppose that the free states of eldricia, a small nation, has consumption, investment, government purchases, imports, and exports as follows. consumption $140 investment $50 government purchases $45 imports $30 exports $15 calculate the free states of eldricia's gdp
Answers: 2
question
Business, 22.06.2019 13:00
Explain the relationship between consumers and producers in economic growth and activity
Answers: 1
question
Business, 22.06.2019 20:00
Which of the following statements is true of the balanced-scorecard? a. it is a more or less a one-dimensional metric of measuring competitive advantages of a firm. b. it is one of the traditional approaches of measuring firm performance. c. its primary focus is to base a firm's strategic goals entirely on external performance dimensions. d. it attempts to provide a holistic perspective on firm performance.
Answers: 1
question
Business, 23.06.2019 07:00
Witch design elements is used to organize used to organize the text in orderly fashion?
Answers: 1
You know the right answer?
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The projec...
Questions
question
Mathematics, 19.11.2020 06:00
question
Mathematics, 19.11.2020 06:00
question
SAT, 19.11.2020 06:00
question
Mathematics, 19.11.2020 06:00
question
Mathematics, 19.11.2020 06:00
question
World Languages, 19.11.2020 06:00
Questions on the website: 13722363