You are creating a schedule duration estimate for the activities in the PDR Project. You’re working with your project and comparing the results of a past similar project to predict the time of the current project. What estimating approach are you using?
A. Organizational process assets
B. Parametric
C. Analogous
D. PERT

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 07:30
Most states have licensing registration requirements for child care centers and family daycare homes. these usually include minimum standard for operation. which of the following would you most likely find required in a statement of state licensing standards for child care centers?
Answers: 2
question
Business, 22.06.2019 10:10
Ursus, inc., is considering a project that would have a five-year life and would require a $1,650,000 investment in equipment. at the end of five years, the project would terminate and the equipment would have no salvage value. the project would provide net operating income each year as follows (ignore income taxes.):
Answers: 1
question
Business, 22.06.2019 11:30
(select all that apply) examples of email use that could be considered unethical include denying receiving an e-mail requesting that you work late forwarding a chain letter asking for donations to a good cause sending a quick message to your friend about last weekend sending your boss the monthly sales figures in an attachment setting up a meeting with your co-worker sharing a funny joke with other employees
Answers: 2
question
Business, 22.06.2019 23:30
Lucido products markets two computer games: claimjumper and makeover. a contribution format income statement for a recent month for the two games appears below: claimjumper makeover total sales $ 30,000 $ 70,000 $ 100,000 variable expenses 20,000 50,000 70,000 contribution margin $ 10,000 $ 20,000 30,000 fixed expenses 24,000 net operating income $ 6,000 required: 1. compute the overall contribution margin (cm) ratio for the company.. 2. compute the overall break-even point for the company in dollar sales. 3. complete the contribution format income statement at break-even point for the company showing the appropriate levels of sales for the two products. (do not round intermediate calculations.)
Answers: 1
You know the right answer?
You are creating a schedule duration estimate for the activities in the PDR Project. You’re working...
Questions
question
Mathematics, 28.05.2021 16:00
question
Mathematics, 28.05.2021 16:00
question
English, 28.05.2021 16:00
Questions on the website: 13722361