On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000.

In 2022, costs incurred were $2,620,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,870,000 and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of $3,920,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
(1) Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method.
(2) Prepare journal entries for 2021 to record the transactions described

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:10
The following transactions occur for badger biking company during the month of june: a. provide services to customers on account for $32,000. b. receive cash of $24,000 from customers in (a) above. c. purchase bike equipment by signing a note with the bank for $17,000. d. pay utilities of $3,200 for the current month. analyze each transaction and indicate the amount of increases and decreases in the accounting equation. (decreases to account classifications should be entered as a negative.)
Answers: 1
question
Business, 22.06.2019 17:30
What do you think: would it be more profitable to own 200 shares of penny’s pickles or 1 share of exxon? why do you think that?
Answers: 1
question
Business, 22.06.2019 19:50
Statistical process control charts: a. indicate to the operator the true quality of material leaving the process. b. display upper and lower limits for process variables or attributes and signal when a process is no longer in control. c. indicate to the process operator the average outgoing quality of each lot. d. display the measurements on every item being produced. e. are a graphic way of classifying problems by their level of importance, often referred to as the 80-20 rule.
Answers: 2
question
Business, 22.06.2019 21:00
The purpose of the transportation approach for location analysis is to minimize which of the following? a. total costsb. total fixed costsc. the number of shipmentsd. total shipping costse. total variable costs
Answers: 1
You know the right answer?
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to b...
Questions
question
History, 14.04.2020 21:03
Questions on the website: 13722367