A large-scale bakery is laying out a new production process for its packaged bread, which it sells to several grocery chains. It takes 12 minutes to bake the bread. How large of an oven is required so that the company is able to produce 4200 units of bread per hour (measured in the number of units that can be baked simultaneously)

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 16:50
Coop inc. owns 40% of chicken inc., both coop and chicken are corporations. chicken pays coop a dividend of $10,000 in the current year. chicken also reports financial accounting earnings of $20,000 for that year. assume coop follows the general rule of accounting for investment in chicken. what is the amount and nature of the book-tax difference to coop associated with the dividend distribution (ignoring the dividends received deduction)?
Answers: 2
question
Business, 22.06.2019 21:30
True or false payroll withholding includes income tax, social security tax, medicare tax as well as money you deduct for your retirement fund.
Answers: 1
question
Business, 22.06.2019 22:30
Using the smith's bbq report, the cost of wine for next week will increase by 2% from the current week. if all other cost of sales stays constant, what will be the approximate total cost of sales for next week?
Answers: 2
question
Business, 22.06.2019 23:00
The sign at the bank reads, "wait here for the first available teller," suggests the use of a waiting line system.a. multiple server, single phaseb. random server, single phasec. single server, multiphased. multiple server, multiphasee. dynamic server, single phase
Answers: 2
You know the right answer?
A large-scale bakery is laying out a new production process for its packaged bread, which it sells t...
Questions
question
Mathematics, 15.12.2021 04:30
question
Mathematics, 15.12.2021 04:30
Questions on the website: 13722367