Business, 09.03.2020 18:16 jenniferpt

Foster Company wants to buy a numerically controlled (NC) machine to be used in producing specially machined parts for manufacturers of trenching machines (to replace an existing manual system). The outlay required is $3,500,000. The NC equipment will last 5 years with no expected salvage value. The expected incremental after-tax cash flows (cash flows of the NC equipment minus cash flows of the old equipment) associated with the project follow:

Year Cash Benefits Cash Expenses
1 $3,900,000 $3,000,000
2 3,900,000 3,000,000
3 3,900,000 3,000,000
4 3,900,000 3,000,000
5 3,900,000 3,000,000

Foster has a cost of capital equal to 10%. The above cash flows are expressed without any consideration of inflation.
Required:
1. Compute the payback period. Round your answer to two decimal places.
years
2. Calculate the NPV and IRR of the proposed project. Use the minus sign to indicate a negative NPV. Round IRR to the nearest percent.

NPV $
IRR %

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 15:20
The beginning inventory is expected to be 2,000 cases. expected sales are 10,000 cases, and the company wishes to begin the next period with an inventory of 1,000 cases. the number of cases the company must purchase during the month is multiple choice 9,000 cases. 10,000 cases. 11,000 cases. 13,000 cases.
Answers: 1
question
Business, 22.06.2019 04:40
Who has summer school : ( because i do : (
Answers: 1
question
Business, 22.06.2019 04:50
Steffi is reviewing various licenses and their uses. match the licenses to their respective uses. you are eligible to work within the state. you are eligible to sell limited investment securities. you are eligible to sell fixed income investment products. your compensation is fee based. section 6 section 7 section 63 section 65
Answers: 3
question
Business, 22.06.2019 19:40
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
You know the right answer?
Foster Company wants to buy a numerically controlled (NC) machine to be used in producing specially...
Questions
question
History, 12.02.2022 04:00
question
Computers and Technology, 12.02.2022 04:00
Questions on the website: 13722359