Business, 10.03.2020 04:37 shay7298

Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have approximately 83 percent (or more precisely 25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project. Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance $ Schedule performance index Cost variance $ Cost performance index

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:50
Your goal is to have $2,000,000. you have a total of $40,000 today. you invest the $40,000 and want to add to it each month. at 10% annual interest, how much do you need to invest each month in order to bring the total up to $2,000,000 30 years from now?
Answers: 2
question
Business, 22.06.2019 07:50
The questions of economics address which of the following ? check all that apply
Answers: 3
question
Business, 22.06.2019 11:30
11.     before adding cream to a simmering soup, you need to a. simmer the cream. b. chill the cream. c. strain the cream through cheesecloth. d. allow the cream reach room temperature. student d   incorrect which answer is right?
Answers: 2
question
Business, 22.06.2019 15:20
On january 2, 2018, bering co. disposes of a machine costing $34,100 with accumulated depreciation of $18,369. prepare the entries to record the disposal under each of the following separate assumptions. exercise 8-24a part 2 2. the machine is traded in for a newer machine having a $50,600 cash price. a $16,238 trade-in allowance is received, and the balance is paid in cash. assume the asset exchange has commercial substance.
Answers: 2
You know the right answer?
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The projec...
Questions
question
Mathematics, 02.12.2020 01:00
question
French, 02.12.2020 01:00
question
Mathematics, 02.12.2020 01:00
question
Mathematics, 02.12.2020 01:00
Questions on the website: 13722362