A particular operation may be performed by two kinds of process. Process A requires a setup time of 40 minutes, whereas Process B requires a setup time of 180 minutes. On the other hand, the per unit run times are: 0.015 minutes on A and 0.0023 minutes on B. Which batch sizes would you route to A and which ones to B?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:30
12.     to produce a textured purée, you would use a/an a. food processor. b. wide-mesh sieve. c. immersion blender d. food mill. student a   incorrect which is correct answer?
Answers: 2
question
Business, 22.06.2019 12:50
Afirm’s production function is represented by q(m,r) = 4m 3/4r1/3, where q denotes output, m raw materials, and r robots. the firm is currently using 6 units of raw materials and 12 robots. according to the mrts, in order to maintain its output level the firm would need to give up 2 robots if it adds 9 units of raw materials. (a) true (b) false
Answers: 3
question
Business, 22.06.2019 15:00
Because gloria's immediate concern was the perceived gender discrimination, she would be more concerned about than intent, resultsresults, intentstatistics, trendsrace,gendergender,race
Answers: 2
question
Business, 22.06.2019 21:30
Consider the following three bond quotes; a treasury note quoted at 87.25, and a corporate bond quoted at 102.42, and a municipal bond quoted at 101.45. if the treasury and corporate bonds have a par value of $1,000 and the municipal bond has a par value of $5,000, what is the price of these three bonds in dollars? multiple choice $872.50, $1,000, $1,000, respectively $1,000, $1,024.20, $1,001.45, respectively $872.50, $1,024.20, $5,072.50, respectively $1,000, $1,000, $1,000, respectively
Answers: 3
You know the right answer?
A particular operation may be performed by two kinds of process. Process A requires a setup time of...
Questions
Questions on the website: 13722360