A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 20:00
Question 6 of 102 pointswhich situation shows a constant rate of change? oa. the number of tickets sold compared with the number of minutesbefore a football gameob. the height of a bird over timeoc. the cost of a bunch of grapes compared with its weightod. the outside temperature compared with the time of day
Answers: 1
question
Business, 23.06.2019 00:10
You are to receive five gold coins from your great uncle as an incentive to study hard. the coins were originally purchased in 1982. your great uncle will deliver the coins the week after finals (assuming your grades are "acceptable"). the amount your great uncle paid for the coins is a(n): indirect cost.overhead cost.opportunity cost.sunk cost.
Answers: 1
question
Business, 23.06.2019 14:00
Marta is twenty eight years old, and she has no dependents. she has saved an emergency fund and an extra $1,500. she would like to save or invest this money in hopes that it will grow fast. marta does not mind taking risks with her money. which type of account or investment is best for her? a. fifteen-year savings bond b. mutual fund c. basic savings account earning 1.3 percent interest, compounded monthly d. ida
Answers: 1
question
Business, 23.06.2019 16:00
Ais what customers expect they will get by purchasing a product. a. brand promise b. a tagline c. warranty d. service mindset select the best answer from the choices provided a b c d
Answers: 2
You know the right answer?
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of...
Questions
Questions on the website: 13722360