During 2019, Tanner Manufacturing expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Tanner applied overhead based on direct labor cost. Actual production required an overhead cost of $290000, $550000 in materials used, and $220000 in labor. All of the goods were completed. What amount was transferred to Finished Goods?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 15:20
Abank has $132,000 in excess reserves and the required reserve ratio is 11 percent. this means the bank could have in checkable deposit liabilities and in (total) reserves.
Answers: 3
question
Business, 22.06.2019 16:00
Advanced enterprises reports year-end information from 2018 as follows: sales (160,250 units) $968,000 cost of goods sold 641,000 gross margin 327,000 operating expenses 263,000 operating income $64,000 advanced is developing the 2019 budget. in 2019 the company would like to increase selling prices by 14.5%, and as a result expects a decrease in sales volume of 9%. all other operating expenses are expected to remain constant. assume that cost of goods sold is a variable cost and that operating expenses are a fixed cost. should advanced increase the selling price in 2019?
Answers: 3
question
Business, 22.06.2019 18:40
Under t, the point (0,2) gets mapped to (3,0). t-1 (x,y) β†’
Answers: 3
question
Business, 22.06.2019 19:50
Managers in a firm hired to improve the firm's profitability and ultimately the shareholders' value will add to the overall costs if they pursue their own self-interests. what does this best illustrate? a. diseconomies of scale b. principal-agent problem c. experience-curveeffects d. information asymmetries
Answers: 1
You know the right answer?
During 2019, Tanner Manufacturing expected Job No. 26 to cost $300000 of overhead, $500000 of materi...
Questions
question
Health, 28.09.2019 22:20
question
Mathematics, 28.09.2019 22:20
Questions on the website: 13722359