Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.

PV = $23,000EV = $20,000AC = $25,000BAC = $120,000What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 14:30
Aconsumer values a house at $525,000 and a producer values the same house at $485,000. if the transaction is completed at $510,000, what level of tax rate will result in unconsummated transaction?
Answers: 2
question
Business, 22.06.2019 11:10
Post test question number 9 for entering the job market
Answers: 1
question
Business, 23.06.2019 12:20
During the economic periods of , the economy is at its highest point and unemployment is low, in addition, total income is high and consumers are willing to buy products and services.
Answers: 1
question
Business, 23.06.2019 14:20
Why does the fed pay interest to banks? a. it is interest on money held in reserve. b. it is interest on credit available to the fed. c. it is interest on loans taken by the fed. d. it is interest on government investments.
Answers: 2
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
Questions on the website: 13722363