Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $23,000EV = $20,000AC = $25,000BAC = $120,000What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
Answers: 3
Business, 21.06.2019 14:30
Aconsumer values a house at $525,000 and a producer values the same house at $485,000. if the transaction is completed at $510,000, what level of tax rate will result in unconsummated transaction?
Answers: 2
Business, 23.06.2019 12:20
During the economic periods of , the economy is at its highest point and unemployment is low, in addition, total income is high and consumers are willing to buy products and services.
Answers: 1
Business, 23.06.2019 14:20
Why does the fed pay interest to banks? a. it is interest on money held in reserve. b. it is interest on credit available to the fed. c. it is interest on loans taken by the fed. d. it is interest on government investments.
Answers: 2
Given the following information for a one-year project, answer the following questions. Recall that...
Mathematics, 14.02.2020 21:13
History, 14.02.2020 21:13
History, 14.02.2020 21:14
History, 14.02.2020 21:14
Mathematics, 14.02.2020 21:14