You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule and costs. Based on your review, You should have spent $50,000 to date based on your initial plans and 100 days activities that were based on the schedule.

You have actually spent $60,000 to date and completed activities for 110 days of the scheduled baseline, which should have cost $45,000 based on your initial plans. Budget required for the remaining work to be completed is estimated at $150,000.

Answer the following

PV (Planned Value) =
AC (Actual Cost) =
EV (Earned Value)=
ETC (Estimate to Complete) =
CPI =
SPI =
CV =
SV =
VAC (Variance at Completion) =
EAC (Estimate at Completion) =
TCPI =

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 10:00
Your father offers you a choice of $120,000 in 11 years or $48,500 today. use appendix b as an approximate answer, but calculate your final answer using the formula and financial calculator methods. a-1. if money is discounted at 11 percent, what is the present value of the $120,000?
Answers: 3
question
Business, 22.06.2019 18:40
Under t, the point (0,2) gets mapped to (3,0). t-1 (x,y) →
Answers: 3
question
Business, 22.06.2019 19:50
What is the present value of the following cash flow stream at a rate of 12.0%? years: 0 1 2 3 4| | | | |cfs: $0 $1,500 $3,000 $4,500 $6,000a. $9,699b. $10,210c. $10,747d. $11,284e. $11,849
Answers: 3
You know the right answer?
You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, yo...
Questions
question
Mathematics, 27.06.2019 15:20
question
Mathematics, 27.06.2019 15:20
question
Mathematics, 27.06.2019 15:20
Questions on the website: 13722359