Lake Erie Company uses a plantwide overhead rate with machine hours as the allocation base. Next year, 770,000 units are expected to be produced taking 0.85 machine hours each. How much overhead will be assigned to each unit produced given the following estimated amounts?Estimated: Department 1 - Department 2
Manufacturing overhead costs - $3,141,500 - $1,571,000
Direct labor hours - 167,000 DLH - 267,000 DLH
Machine hours - 267,000 MH - 192,000 MH
a. $10.86 per unit
b. $8.73 per unit
c. $4.22 per unit
d. $11.77 per unit
e. $10 per unit

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 08:00
Interest is credited to a fixed annuity no lower than the variable contract rate contract guaranteed rate current rate of inflation prime rate
Answers: 2
question
Business, 22.06.2019 09:50
The returns on the common stock of maynard cosmetic specialties are quite cyclical. in a boom economy, the stock is expected to return 22 percent in comparison to 9 percent in a normal economy and a negative 14 percent in a recessionary period. the probability of a recession is 35 percent while the probability of a boom is 10 percent. what is the standard deviation of the returns on this stock?
Answers: 2
question
Business, 22.06.2019 11:20
Stock a has a beta of 1.2 and a standard deviation of 20%. stock b has a beta of 0.8 and a standard deviation of 25%. portfolio p has $200,000 consisting of $100,000 invested in stock a and $100,000 in stock b. which of the following statements is correct? (assume that the stocks are in equilibrium.) (a) stock b has a higher required rate of return than stock a. (b) portfolio p has a standard deviation of 22.5%. (c) portfolio p has a beta equal to 1.0. (d) more information is needed to determine the portfolio's beta. (e) stock a's returns are less highly correlated with the returns on most other stocks than are b's returns.
Answers: 3
question
Business, 22.06.2019 12:10
This exercise illustrates that poor quality can affect schedules and costs. a manufacturing process has 130 customer orders to fill. each order requires one component part that is purchased from a supplier. however, typically, 3% of the components are identified as defective, and the components can be assumed to be independent. (a) if the manufacturer stocks 130 components, what is the probability that the 130 orders can be filled without reordering components? (b) if the manufacturer stocks 132 components, what is the probability that the 130 orders can be filled without reordering components? (c) if the manufacturer stocks 135 components, what is the probability that the 130 orders can be filled without reordering components?
Answers: 3
You know the right answer?
Lake Erie Company uses a plantwide overhead rate with machine hours as the allocation base. Next yea...
Questions
question
Social Studies, 18.11.2019 19:31
question
Mathematics, 18.11.2019 19:31
Questions on the website: 13722362