Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building that is expected to be completed in September 2023, at an estimated cost of $22,000,000. At the end of 2021, the costs to date were $10,120,000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $4,800,000 and the cash collected during 2021 was 3,200,000. Cooper uses the percentage-of-completion method.

For the year ended December 31, 2021, Cooper would recognize gross profit on the building of:

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:40
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the company’s 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
question
Business, 22.06.2019 17:30
After the embarrassing sign incident at the restaurant you own, you decide to offer employees a six-week fundamental writing skills workshop. a local business communication instructor, who has experience teaching writing skills at treleaven community college, will facilitate the sessions. to encourage employees to attend these optional sessions, write an email that explains why you’re offering the workshop and why employees should participate.
Answers: 2
question
Business, 23.06.2019 01:00
Apopular low-cost airline, parson corp., has gone out of business. although the service and price provided by the airline was what customers wanted, the larger airlines were able to drive the low-cost airline out of business through an aggressive price war. which component of the competitive environment does this illustrate?
Answers: 3
question
Business, 23.06.2019 15:00
Wilmington company has two manufacturing departments--assembly and fabrication. it considers all of its manufacturing overhead costs to be fixed costs. the first set of data that is shown below is based on estimates from the beginning of the year. the second set of data relates to one particular job completed during the year--job bravo. estimated data assembly fabrication total manufacturing overhead costs $ 6,720,000 $ 7,280,000 $ 14,000,000 direct labor-hours 140,000 84,000 224,000 machine-hours 56,000 280,000 336,000 job bravo assembly fabrication total direct labor-hours 29 21 50 machine-hours 21 24 45 required: 1. if wilmington used a plantwide predetermined overhead rate based on direct labor-hours, how much manufacturing overhead would be applied to job bravo
Answers: 3
You know the right answer?
Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building...
Questions
question
Mathematics, 16.11.2019 05:31
Questions on the website: 13722367