Business, 21.04.2020 18:57 stmy1969

Bisutti Cams is producing its Racing Camshaft models RC1 and RC2. It is a three-state process that involves collecting the appropriate items from inventory, assembling, and then inspecting them. Bisutti Cams is making its labor estimates for the next four quarters for the collecting, assembling and inspecting operations. The RC1 requires 5 hours of labor and the RC2 requires 2 hours. The collecting process uses 20% of its labor resources, the assembling uses 70%, and the inspecting uses 10%. The production schedule for the next four quarters is given below.

Calculate the labor hours required in the collecting, assembling, and inspecting processes for the next four quarters.

Quarter
Endproduct 1 2 3 4
RC I 100 120 200 140
RC 2 200 250 150 100

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 22:10
You have just received notification that you have won the $2.0 million first prize in the centennial lottery. however, the prize will be awarded on your 100th birthday (assuming you're around to collect), 66 years from now. what is the present value of your windfall if the appropriate discount rate is 8 percent?
Answers: 1
question
Business, 22.06.2019 11:30
Mai and chuck have been divorced since 2012. they have three boys, ages 6, 8, and 10. all of the boys live with mai and she receives child support from chuck. mai and chuck both work and the boys need child care before and after school. te boys attend the fun house day care center and mai paid them $2,000 and chuck paid them $3,000. mai's agi is $18,000 and chuck's is $29,000. mai will claim two of the boys as dependents. she signed form 8332 which allows chuck to claim one of the boys. who can take the child and dependent care credit?
Answers: 3
question
Business, 22.06.2019 19:50
Aproduction line has three machines a, b, and c, with reliabilities of .96, .86, and .85, respectively. the machines are arranged so that if one breaks down, the others must shut down. engineers are weighing two alternative designs for increasing the line’s reliability. plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. in either case, three machines (a, b, and c) would be used with reliabilities equal to the original three. a. compute overall system reliability under plan 1. (round your intermediate calculations and final answer to 4 decimal places.) reliability b. compute overall system reliability under plan 2. (round your intermediate calculations and final answer to 4 decimal places.) reliability c. which plan will provide the higher reliability? plan2plan1
Answers: 3
question
Business, 22.06.2019 23:40
Gif the federal reserve did not regulate fiscal policy, monitor banks and provide services for banks, what would most likely be the economic conditions to transact business in the u.s.? the economy would primarily be based on a barter system rather than a fiat system. there would be no discrimination in lending by local banks. the economy would be less efficient and transactions most likely more costly.
Answers: 1
You know the right answer?
Bisutti Cams is producing its Racing Camshaft models RC1 and RC2. It is a three-state process that i...
Questions
question
Mathematics, 16.03.2022 17:30
question
Mathematics, 16.03.2022 17:30
question
History, 16.03.2022 17:30
question
History, 16.03.2022 17:40
Questions on the website: 13722361