The following tasks lie on the critical path of a project:
Task Mean Completion Time St. Dev
A 4 0.6
B 5 0.2
E 2 0.1
F 6 1
H 2 0.2
M 6 0.1
The above task gives the mean completion time of each task (in days) and the standard deviation.
1. Based on this information, what is the probability that the project will be completed in 23 days or less?
a. Less than 5% but more than 3%
b. Less than 3%
c. More than 5% but less than 10%
d. None of the above

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 00:00
When is going to be why would you put money into saving account
Answers: 1
question
Business, 22.06.2019 11:00
If the guide wprds on the page are "crochet " and "crossbones", which words would not be on the page. criticize, crocodile,croquet,crouch,crocus.
Answers: 1
question
Business, 22.06.2019 13:10
The textbook defines ethics as “the principles of conduct governing an individual or a group,” and specifically as the standards one uses to decide what their conduct should be. to what extent do you believe that what happened at bp (british petrolium) is as much a breakdown in the company’s ethical systems as it is in its safety systems, and how would you defend your conclusion?
Answers: 2
question
Business, 22.06.2019 18:30
Jason started last week with $900 in his checking account. during the week, he wrote the checks below. at the end of the week, jason received a paycheck for $534.59. he recorded all of these transactions in his check register. trans typ./ check no. date description of transaction payment/ debit deposit/ credit (+) balance 900 00 241 12/4 miller's food market 53.21 53 21 groceries 846 79 242 12/7 frank's auto parts 24.05 24 05 oil and filter 822 74 243 12/8 mike's barber shop 15.00 15 00 haircut 807 74 deposit 12/9 paycheck 534.59 534 59 1,342 33 evaluate jason's check register. a. jason did a good job; everything is correct. b. the final balance is wrong; jason did not add everything correctly. c. jason should have written debit instead of deposit for the transaction type. d. jason entered the amount for his paycheck in the wrong column.
Answers: 3
You know the right answer?
The following tasks lie on the critical path of a project:
Task Mean Completion Time St. Dev...
Questions
question
Computers and Technology, 21.10.2019 14:50
question
Computers and Technology, 21.10.2019 14:50
question
Mathematics, 21.10.2019 14:50
question
Mathematics, 21.10.2019 14:50
Questions on the website: 13722361