The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek:
Task Performance Time (seconds) Predecessors
A 22 -
B 30 A
C 15 A
D 14 A
E 12 B, C
F 27 D, E
Required:
a) Given the demand, the cycle time for the production of the new train set = (round your response to one decimal place).
b) The theoretical minimum number of work stations is ? (round your response up to the next whole number)

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 19:00
Which of the following would cause a shift to the right of the supply curve for gasoline? i. a large increase in the price of public transportation. ii. a large decrease in the price of automobiles. iii. a large reduction in the costs of producing gasoline
Answers: 1
question
Business, 22.06.2019 20:20
An economic theory that calls for workers to take control of factories is .
Answers: 3
question
Business, 22.06.2019 22:20
Which of the following is one disadvantage of renting a place to live compared to buying a home? a. tenants have to pay for all repairs to the building. b. the landlord covers the expenses of maintaining the property. c. residents can't alter their living space without permission. d. rent is generally more than monthly mortgage payments.
Answers: 1
question
Business, 23.06.2019 13:30
the social-cultural environment a firm operates in is constantly changing, and having a significant impact on marketing strategies. the change is so rapid and immense that some firms have created a new position in the organization to handle this change. which title best describes the new position described in the scenario?
Answers: 3
You know the right answer?
The Action Toy Company has decided to manufacture a new train set, the production of which is broken...
Questions
question
History, 09.12.2020 20:10
question
Geography, 09.12.2020 20:10
Questions on the website: 13722367